SANITARY SEWER REHABILITATION
& WWTP IMPROVEMENTS PROJECT PLANS

WORK BEGINS THE WEEK OF APRIL 15, 2024


NASHVILLE SANITARY SEWER REHABILITATION & WWTP IMPROVEMENTS PER APRIL 2021

NASHVILLE SANITARY SEWER REHABILITATION & WWTP IMPROVEMENTS PER REVISION DECEMBER 2023

Sanitary Sewer Cleaning and Camering and Lining will begin April 15, 2024.

Part one of the project will be cleaning, camering and lining of the Town’s sewer system. You will see trucks and machinery throughout town, please allow them space to do their work so they can get in and out of your area quickly. The work in the business district will be done overnight to mitigate disturbance of businesses during the day.

Lining of the Lateral Lines
When lining lateral drains, every drain needs to have water in the drain lines. You can run the water for two minutes prior to the work in your area. For those with basement drains, cover the drain with a wet rag so mitigate the glue like smell for 3-4 days. The basement could be aired out after the work by fanning out the smell out your windows.

Calendar and Maps of Work

If you are interested in knowing when construction will be by you, follow the list to see what day construction will be happening and where. Each date will be above a map with the construction route for the corresponding day.
* All work schedules are dependant upon the weather and will be adjusted accordingly.
We will do our best to update this page as we receive more information from the contractors.

April 29, 2024

April 30, 2024

May 1, 2024

May 2, 2024